Project Management Professional (PMP) — Question 25
A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders. The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts, which are listed on the project risk matrix.
What should the project manager do with regard to community engagement in this situation?
Answer options
- A. Build channels to extend communication efforts to the local community.
- B. Focus on the sideward stakeholders only and let the organization manage the community.
- C. Use the city administration to address communication with the community.
- D. Include the local union representative in the high-power, high-impact stakeholder group.
Correct answer: A
Explanation
The correct answer is A because establishing communication channels is essential for addressing community concerns and fostering transparency. Option B is incorrect as ignoring community engagement can lead to misinformation and distrust. Option C is not ideal since relying solely on city administration might weaken direct community relations, and option D, while beneficial for union relations, does not directly address the broader community engagement needed.