Project Management Professional (PMP) — Question 242

A key project team member is out on sick leave in the middle of a critical project iteration. The project sponsor learns that any delay with the end-of-iteration release will displease the business stakeholders. Although all team members are cross-functional, they are also working close to full capacity.

What should the project manager do to address this situation?

Answer options

Correct answer: B

Explanation

The correct answer is B because it allows the team to reassess priorities and focus on the most critical tasks, ensuring that the release deadline is met despite the absence. Option A may lead to burnout as team members take on additional work without adjusting priorities. Option C does not address the immediate need for task prioritization, while option D simply communicates the problem without seeking a proactive solution.