Project Management Professional (PMP) — Question 240
A company's key product is evolving and requires the use of a new technology. No one on the team is familiar with this technology; however, experienced developers on the team volunteered to study the concepts and application and believe they will be able to take full responsibility for the new technology.
What should the project manager do?
Answer options
- A. Outsource the technology work to a third party so as not to delay work.
- B. Descope this requirement as the developers have more important tasks.
- C. Hire externally since the internal developers already have assigned work.
- D. Support the developers with their intention to learn the new technology.
Correct answer: D
Explanation
The correct answer is D because supporting the developers in learning the new technology allows the team to build internal expertise, which is beneficial for long-term project success. Options A and C suggest outsourcing, which may not be ideal for team development and knowledge retention. Option B suggests removing the requirement, which may hinder the product's evolution and adaptability.