Project Management Professional (PMP) — Question 235

A project manager receives a voicemail from a business analyst on the project team. The business analyst indicates that an internal stakeholder is upset that they were not included before the project began. The stakeholder is asking for an addition to the requirements traceability matrix.
What should the project manager do to improve the stakeholder relationship?

Answer options

Correct answer: C

Explanation

The correct answer is C because engaging the stakeholder for more information shows that their input is valued and helps clarify the request. Options A and B do not directly address the relationship issue, and D may delay action as it involves formal change request processes, which may not be necessary at this stage.