Project Management Professional (PMP) — Question 221
A project is on its second iteration out of six. The team realizes that a key deliverable will depend on the acquisition of a new device.
What should the project manager do?
Answer options
- A. Invite the stakeholders to discuss prioritization of a new deliverable.
- B. Detail the reason for the deliverable delay in the status report.
- C. Register a risk and escalate it to the project sponsor.
- D. Include the responsibility for acquisition with the core team.
Correct answer: C
Explanation
The correct answer is C because registering the risk and escalating it to the project sponsor ensures that the issue is formally acknowledged and addressed at a higher level. Option A, while involving stakeholders, does not directly address the risk of delay. Option B only communicates the problem without taking proactive measures, and option D shifts responsibility but does not mitigate the risk associated with the deliverable dependency.