Project Management Professional (PMP) — Question 195

A project's customer is furious. When the customer arrived at the project site, they discovered that one of their requirements was not met.
What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because referring to the requirements traceability matrix allows the project manager to verify which requirements were documented and whether the missing requirement was included. Options A, C, and D may involve discussions and reviews, but they do not focus on analyzing the documentation that confirms the original requirements, which is crucial in this scenario.