Project Management Professional (PMP) — Question 18
A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.
What advice should the senior project manager provide?
Answer options
- A. Work with the project manager to develop a new approach that will bring benefits to the project
- B. Suggest using an agile approach since customer and team collaboration is critical for project success
- C. Establish a project management methodology that requires the customer to provide daily updates to the team
- D. Provide a project management template for the project manager to follow as a guide
Correct answer: B
Explanation
The correct answer is B because an agile approach emphasizes continuous collaboration and flexibility, which is crucial when working closely with stakeholders. Options A, C, and D do not specifically address the need for strong collaboration, which is highlighted as a key factor in the project’s success.