The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path.
What should the project manager do in this situation?

Answer options

Correct answer: B

Explanation

The correct action is to review the critical path with the stakeholders, as this helps to establish a clear understanding of the project's priorities and potential adjustments. Discussing issues with the purchasing department (A) or the work breakdown structure with suppliers (C) may not directly address the immediate scheduling concerns. Escalating to the sponsor (D) could be premature without first assessing the situation with the stakeholders.