Project Management Professional (PMP) — Question 157

By the end of the first sprint, a project lead notices that one of the team members is not performing very well.

Which form of communication should the project lead use to handle the situation?

Answer options

Correct answer: D

Explanation

The correct answer is D, as informal verbal communication allows for a more relaxed and open dialogue, which can help the team member feel more comfortable discussing their challenges. Options A and C are more formal and may not encourage an honest conversation, while option B, although verbal, is also formal and may not be appropriate for addressing immediate performance issues.