Project Management Professional (PMP) — Question 156

A project manager has just been appointed to a project that has two major deliverables. Both deliverables have the same level of priority and are to be delivered at the same time. The members of the team are complaining about the lack of information regarding which deliverable needs to be finished first.

What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because consulting with the project sponsor and stakeholders helps clarify the priorities based on organizational value, which can provide direction to the team. Answer B is not a viable solution as canceling the project is extreme and does not address the issue at hand. C is incorrect because starting with the easiest deliverable does not align with the priority of the project. D is also wrong since executing both deliverables simultaneously without clarity can lead to confusion and inefficiency.