Project Management Professional (PMP) — Question 145

In a frequently changing project, the project manager discovers a customer requirement change during a daily meeting. What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because validating the requirement change with the product owner and development team ensures that the change is understood and properly assessed before any adjustments to the project scope are made. Options A and B incorrectly suggest escalating or delaying the change without proper evaluation, while option C fails to involve the necessary stakeholders in the decision-making process.