Project Management Professional (PMP) — Question 142

The project manager is reviewing a project's progress and notices that one of the risks has become an issue.
What should the project manager do to address the situation?

Answer options

Correct answer: D

Explanation

The correct answer is D because collaborating with stakeholders to execute the risk response plan directly addresses the issue that has arisen. Options A and C are reactive measures that may not effectively resolve the issue, while option B, although useful for brainstorming, does not take immediate action to manage the risk that has become an issue.