Project Management Professional (PMP) — Question 1407
A team is ready to start working on a project with a customer who was very difficult to work with in the past because the customer was unable to describe exactly what they wanted.
What approach should the project manager take to remove this impediment?
Answer options
- A. Follow a predictive approach in order to obtain formal acceptance of each deliverable
- B. Work with the product owner to define the minimum viable product(s)
- C. Reinforce the negotiation and soft skills of the team through training
- D. Develop and monitor a plan with due dates to reduce the time of completing the product
Correct answer: B
Explanation
The correct answer is B because defining the minimum viable product(s) helps clarify the customer's needs and sets a foundation for the project. Options A and D focus on formal processes and timelines, which may not address the customer's lack of clarity. Option C, while beneficial for team development, does not directly resolve the immediate communication issues with the customer.