Project Management Professional (PMP) — Question 1407

A team is ready to start working on a project with a customer who was very difficult to work with in the past because the customer was unable to describe exactly what they wanted.
What approach should the project manager take to remove this impediment?

Answer options

Correct answer: B

Explanation

The correct answer is B because defining the minimum viable product(s) helps clarify the customer's needs and sets a foundation for the project. Options A and D focus on formal processes and timelines, which may not address the customer's lack of clarity. Option C, while beneficial for team development, does not directly resolve the immediate communication issues with the customer.