Project Management Professional (PMP) — Question 1406
An agile project is in its eighth iteration out of 16. After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply.
Which two actions should the project manager take? (Choose two.)
Answer options
- A. Ask the product owner to include the requirements in the product backlog.
- B. Ask the security department for details about regulations.
- C. Ask the stakeholders about the priority of this regulation.
- D. Ask the team members to include the requirements in the next iteration.
- E. Ask the team members to analyze the impact of including this regulation.
Correct answer: B, E
Explanation
The correct actions are to ask for details about the regulations and to have team members analyze the impact of including these regulations. While including the requirements in the backlog or discussing priorities with stakeholders are important, they are not immediate actions that address the need for understanding and assessing the implications of compliance.