Project Management Professional (PMP) — Question 1396
A project manager was just assigned to a project as the leader of an experienced agile team. How should the project manager influence the team to accomplish the project objectives?
Answer options
- A. Assert judgment over the team.
- B. Increase the amount of subject matter experts (SMEs) to get better results.
- C. Use a plan-driven approach in order to demonstrate control over the project.
- D. Express trust in the team’s ability to fulfill the necessary deliverables.
Correct answer: D
Explanation
The correct answer, D, emphasizes the importance of trust in an agile environment, empowering the team to take ownership of their work. Options A and C undermine the agile principles by promoting control rather than collaboration, while B may not be necessary if the existing team is already experienced and capable.