Project Management Professional (PMP) — Question 1387

A primary stakeholder is unable to join the project status meetings consistently. The project manager has been communicating with this stakeholder informally and regularly to ensure that the stakeholder is up to date on the project. However, the project manager has recently resigned and will not be meeting with the new project manager prior to departure.
How should the project manager ensure that the new project manager continues to update this particular stakeholder?

Answer options

Correct answer: B

Explanation

The correct answer is B because updating the stakeholder engagement plan ensures that the new project manager is aware of the communication preferences and needs of the stakeholder. Options A and C, while helpful, do not specifically address the need for updated communication strategies. Option D focuses on the overall communication management plan rather than the specific engagement requirements for this particular stakeholder.