Project Management Professional (PMP) — Question 1386
A project manager wants to make sure that similar projects in the future use the project's performance data as a reference. However, the project manager is not sure how to accomplish this.
What should the project manager do?
Answer options
- A. Keep project artifacts up-to-date and accessible to all stakeholders
- B. Share project documentation in a repository with exclusive access
- C. Schedule weekly knowledge-sharing sessions with key stakeholders
- D. Send periodic emails to senior management with the latest project updates
Correct answer: A
Explanation
The correct answer is A because maintaining project artifacts that are up-to-date and accessible allows all stakeholders to reference and learn from the project's performance data. Options B and C limit access or do not ensure that the information is readily available for future projects, while option D relies on periodic communication rather than consistent accessibility.