Project Management Professional (PMP) — Question 1384

During the lessons learned workshop, one stakeholder mentioned that the project was unsuccessful as it did not deliver the expected business value.
What should the project manager do to address this concern?

Answer options

Correct answer: B

Explanation

The correct answer is B because reviewing the business benefits realization plan allows the project manager to understand how the project was intended to deliver value and identify any gaps. The other options focus on different aspects of project management that do not directly address the concern of business value delivery.