During the lessons learned workshop, one stakeholder mentioned that the project was unsuccessful as it did not deliver the expected business value.
What should the project manager do to address this concern?
Answer options
- A. Review the project management plan tasks with the stakeholders.
- B. Review the business benefits realization plan with the stakeholders.
- C. Review the project management plan budget with the stakeholders.
- D. Review the communications management plan with the stakeholders.
Correct answer: B
Explanation
The correct answer is B because reviewing the business benefits realization plan allows the project manager to understand how the project was intended to deliver value and identify any gaps. The other options focus on different aspects of project management that do not directly address the concern of business value delivery.