Project Management Professional (PMP) — Question 1383

A team has just adopted an agile approach. During daily standup meetings, the team expressed concerns about task delays. The project leader worked with the product owner to get clarity on the features. The project leader asked the team to fast-track all product features to ensure delivery. Sprints are being completed but with either fewer features or low quality.
What should the project leader have done to ensure success?

Answer options

Correct answer: D

Explanation

The correct answer is D because empowering the team allows them to take ownership of their processes and encourages continuous improvement, which is crucial for agile success. Options A, B, and C are more reactive and do not provide the team with the autonomy and responsibility needed to drive effective change and quality delivery.