Project Management Professional (PMP) — Question 137

A project team is having difficulties understanding technical details regarding requirements. The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished.
How should the project manager approach this situation?

Answer options

Correct answer: A

Explanation

The correct answer is A because directly asking the customer to clarify feature definitions ensures that the project team gets the precise information needed for the current sprint. Options B and C do not directly address the need for clarification on requirements, while D may lead to delays in obtaining immediate information necessary for the sprint.