Project Management Professional (PMP) — Question 1365
The sponsor is supportive in leveraging agile approaches. The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders.
What should the project manager do first?
Answer options
- A. Determine which agile software tools will be required to support agile delivery within the organization
- B. Select a current predictive project, define the approach, and provide agile training to execute the remainder of the project
- C. Start with a pilot project of appropriate complexity, and provide agile training to those who are impacted
- D. Determine how to transform the organization using agile techniques, including organizational training and communications
Correct answer: C
Explanation
The correct answer is C because starting with a pilot project allows for a controlled environment to test the agile approach and gather feedback, which is crucial for gaining buy-in. Options A and B focus too much on tools and existing projects without addressing the need for training and adaptation, while D is overly broad and doesn't concentrate on immediate action.