Project Management Professional (PMP) — Question 1361

After a couple of iterations, the project manager decides to present the product to a key stakeholder. The stakeholder's feedback is that the team missed the mark on many features.
What should the project manager do to avoid this in the future?

Answer options

Correct answer: B

Explanation

The correct answer, B, emphasizes the importance of regular sprint demos to obtain feedback early on, allowing for adjustments to be made before the project reaches later stages. Option A suggests gathering requirements, which is important but does not ensure ongoing feedback during development. Option C focuses on design thinking, which is beneficial but not as immediate as obtaining feedback through sprint demos. Option D does not address the feedback loop needed to understand stakeholder expectations throughout the project.