Project Management Professional (PMP) — Question 1357

An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan. The project team evaluated the product's feasibility of functionality and accelerated testing.
What should the project manager do as a servant leader?

Answer options

Correct answer: A

Explanation

The correct answer is A because as a servant leader, the project manager's role is to support the team in reaching their goals, which includes identifying the MVP. Options B and C are not the immediate focus for a servant leader, as they involve budget and change management rather than team support. Option D focuses on adherence to the schedule but does not prioritize the team's needs or MVP identification.