Project Management Professional (PMP) — Question 1356
Some members of a project team are frustrated by a new team member who previously worked in a Scrum setting. This new team member approaches members of the project team on a daily basis in what appears to be an attempt to engage in individual standup meetings.
What should the project manager do?
Answer options
- A. Schedule a meeting for the project team to review the communications management plan.
- B. Tell the rest of the project team to continue discussions with the new team member.
- C. Send an email to the project team outlining the communications strategy.
- D. Mentor the new team member on the methodology the project team is using.
Correct answer: D
Explanation
The correct answer is D because mentoring the new team member helps them understand the project team's methodology and aligns their approach with the team's practices. Options A, B, and C do not address the root cause of the frustration and may not effectively integrate the new member into the team dynamics.