Project Management Professional (PMP) — Question 1327
A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.
When should the value be demonstrated?
Answer options
- A. After full development is completed
- B. When the sponsor approves the increment
- C. When a major feature is completed
- D. At the end of each and every iteration
Correct answer: D
Explanation
The correct answer is D, as demonstrating value at the end of each iteration allows stakeholders to see progress and provide feedback regularly. Options A and C delay value demonstration until later stages, which can hinder timely adjustments, while option B relies on sponsor approval rather than a proactive demonstration of value.