Project Management Professional (PMP) — Question 1326

An organization is transitioning to an agile approach. At the project’s first sprint review, the product owner did not accept the result of the sprint and has some concerns.

What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because organizing a sprint retrospective allows the team to collaboratively identify and address the product owner's concerns, fostering improvement. Options A and C neglect the need for discussion and collaboration, while B focuses on escalation rather than resolution within the agile framework.