Project Management Professional (PMP) — Question 1317

A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule.
What should project manager to do next to minimize the impact on the project?

Answer options

Correct answer: D

Explanation

The correct answer is D because reviewing the issue log and exploring alternatives allows the project manager to proactively address the delay and find solutions. Option A may not be feasible if stakeholders do not agree to the extension. Option B could lead to further delays due to the onboarding process of a new vendor, and option C does not address the immediate need for a solution.