Project Management Professional (PMP) — Question 1311

A critical deliverable for the current iteration is giving the team difficulties. Functionality and quality issues are constantly emerging and delaying iteration progress.
The project manager listens to the team's concerns and discovered that the work is not being well coordinated among the team members.
Which two actions should the project manager take to handle this situation? (Choose two.)

Answer options

Correct answer: C, E

Explanation

The correct actions are to schedule an iteration backlog refinement meeting (C) to gain insights into the team's difficulties and to prioritize the issues affecting the iteration goal (E). The other options, while potentially beneficial, do not directly address the immediate coordination problems that are causing the delays.