Project Management Professional (PMP) — Question 1290

The city has decided to build a new tram station. The project will include various approaches. The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle. Some neighbors are resisting the project have been asking the mayor to stop the project, and are threatening legal action.
What two actions should the project manager take'? (Choose two.)

Answer options

Correct answer: D, E

Explanation

Option D is correct because engaging with neighbors can help address their concerns and foster support for the project. Option E is also correct as recognizing this situation as a risk and developing a mitigation plan is essential for managing potential legal challenges. Options A, B, and C, while relevant, do not directly address the immediate need to involve the neighbors or manage the risk effectively.