A project manager wants to ensure that the project acceptance criteria are met for all project deliverables. What should the project manager do to accomplish this?

Answer options

Correct answer: B

Explanation

The correct answer, B, highlights the importance of including stakeholder needs in the acceptance criteria, which ensures that the deliverables meet their expectations. Option A is incorrect because a SOW may need adjustments during the project. Option C, while beneficial for communication, does not directly ensure that acceptance criteria are met. Option D is not sufficient on its own, as it only involves discussion without the active engagement of stakeholder needs in the criteria.