Project Management Professional (PMP) — Question 1282

In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.

What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct choice is D because it involves documenting the issue and referring to the resource management plan, which is essential for managing team resources effectively. Option A may not be feasible as it relies on the sponsor's availability, B could jeopardize project goals without assessing impacts, and C could lead to burnout or decreased quality of work without addressing the root issue.