Project Management Professional (PMP) — Question 1282
In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.
What should the project manager do?
Answer options
- A. Ask the sponsor for an experienced team member in the company to help the project team.
- B. Reduce the scope of the project and inform stakeholders.
- C. Ask the team for extra work to fulfill the project commitment.
- D. Update the issue log and refer to the resource management plan to address the situation.
Correct answer: D
Explanation
The correct choice is D because it involves documenting the issue and referring to the resource management plan, which is essential for managing team resources effectively. Option A may not be feasible as it relies on the sponsor's availability, B could jeopardize project goals without assessing impacts, and C could lead to burnout or decreased quality of work without addressing the root issue.