Project Management Professional (PMP) — Question 1275
A project team with members from many different countries is struggling to cooperate. The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase. The project is beginning to fall behind schedule.
What can the project manager do to move the team to the norming phase?
Answer options
- A. Plan social activities to help foster stronger interpersonal relationships and identify shared goals.
- B. Figure out who is behind the issues and apply progressive disciplinary techniques.
- C. Speak with the project sponsor about changing the team composition.
- D. Show the team the schedule impact of their communication issues and encourage them to put their differences aside.
Correct answer: A
Explanation
The correct answer is A because planning social activities can enhance team bonding and help members find common ground, which is crucial for moving to the norming phase. Options B and C focus on punitive or structural changes, which may not address the underlying interpersonal issues, while option D, although relevant, may not be as effective in fostering collaboration as building relationships.