Project Management Professional (PMP) — Question 1275

A project team with members from many different countries is struggling to cooperate. The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase. The project is beginning to fall behind schedule.
What can the project manager do to move the team to the norming phase?

Answer options

Correct answer: A

Explanation

The correct answer is A because planning social activities can enhance team bonding and help members find common ground, which is crucial for moving to the norming phase. Options B and C focus on punitive or structural changes, which may not address the underlying interpersonal issues, while option D, although relevant, may not be as effective in fostering collaboration as building relationships.