Project Management Professional (PMP) — Question 1246

A project manager is attending a progress meeting with a client. The client requests a design change which might potentially add value to the project.

What action should the project manager take?

Answer options

Correct answer: D

Explanation

The correct answer is D because the project manager should prioritize decisions that align with the overall project goals. Options A and B involve giving decision-making power to others or accommodating changes without consideration of project objectives. Option C suggests opposing the client's request without addressing its potential benefits.