Project Management Professional (PMP) — Question 1223

A transportation company is transforming its operational processes and the main system this company uses to move freight. The scope statement is in place. An iterative delivery approach has been agreed by all stakeholders.
What does the project manager need to do next to help the team understand the work that needs to be done?

Answer options

Correct answer: B

Explanation

The correct answer is B because breaking down the scope into a Work Breakdown Structure (WBS) helps clarify the tasks and deliverables necessary for the project. Options A and C focus on planning aspects that come after the WBS is established, while option D involves stakeholder engagement but does not prioritize the team's understanding of the scope breakdown.