During a daily standup meeting, a roadblock was raised that is preventing one of the team members from proceeding with work. The project manager figures out that it is due to a technical issue.
What should the project manager do to prioritize this critical impediment?
Answer options
- A. Solve the issue for the team member.
- B. Perform a brainstorming session to address the issue and add the solution to the sprint.
- C. Escalate the issue to the software vendor for technical resolution.
- D. Coach the team to come up with their own solution and add it to the next sprint.
Correct answer: B
Explanation
The correct answer is B because a brainstorming session allows the team to collaboratively identify potential solutions, which can then be prioritized and added to the sprint. Answer A is incorrect as it takes away ownership from the team. C is not ideal since it delays resolution and might not engage the team. D, while encouraging teamwork, lacks immediate action to resolve the current impediment.