Project Management Professional (PMP) — Question 1185

Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared. Management asks the project manager to move forward with the project without an approved project scope statement.
What should the project manager do next?

Answer options

Correct answer: C

Explanation

The correct answer is C because the project manager should communicate the risks associated with proceeding without a project scope statement to management. Option A does not directly address the immediate issue at hand, while Option B is not a constructive response and Option D could lead to significant issues later on due to lack of clarity in project objectives.