A project manager is initiating an agile project for which some external components will be delivered by vendors. One of the vendors, however, will be unable to deliver its component in an incremental, collaborative way.
How should the project manager handle this situation?

Answer options

Correct answer: C

Explanation

The correct answer is C because it allows for the integration of the vendor's component without compromising the overall agile framework of the project. Option A is incorrect as replacing the vendor may not be feasible or necessary. Option B is not ideal since it undermines the agile approach that the project is based on. Option D delays the component's delivery unnecessarily when it could be integrated using a different method.