An agile project is running activities to define the minimum viable product (MVP). During the session, the project manager identifies some mandatory regulations, but there is no consensus to include these regulations in the MVP because it may extend the duration of the project.
What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because it emphasizes the importance of complying with mandatory regulations, which are crucial for the project's success, despite the potential delay. Option A does not address the need for compliance, while C suggests ignoring critical regulations, and D does not involve the team in the decision-making process regarding the MVP.