Project Management Professional (PMP) — Question 117

At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.

How should the project manager reply?

Answer options

Correct answer: A

Explanation

The correct answer, A, indicates that the budget was created using probabilistic analysis, which is a valid method for anticipating uncertainties. Options B, C, and D do not directly address the development of the budget in relation to future uncertainties, making them less relevant in this context.