Project Management Professional (PMP) — Question 1172
A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case.
What should the project manager do?
Answer options
- A. Ensure the client representative is involved in the estimation.
- B. Ensure that a 20% contingency is included in the estimation.
- C. Review the completion costs of similar projects.
- D. Review the lessons learned from similar projects.
Correct answer: C
Explanation
The correct answer is C, as reviewing the completion costs of similar projects provides a realistic benchmark for estimating costs. Options A and B focus on involvement and contingency planning, which are important but do not directly inform cost estimation. Option D, while useful for improving future projects, does not directly aid in providing a cost estimate for the current project.