Project Management Professional (PMP) — Question 1165

In an agile project, the team decided to have a rotating group of facilitators for the daily scrum. Overall, most of the facilitators have grown and done well in this role; however, a few of them tend to run inefficient daily scrums.
What should the project manager do next?

Answer options

Correct answer: A

Explanation

The correct answer is A because it supports the team's growth and self-organization while offering targeted support to those struggling. Option B undermines the team's autonomy by reverting to a single facilitator, while C may discourage development by removing opportunities for less effective facilitators. Option D could be excessive, as only a few facilitators are underperforming, and retraining everyone may not be necessary.