Project Management Professional (PMP) — Question 1164
A project manager is leading a product feature rollout that will gain more subscribers for a video-streaming application. During the backlog grooming phase. the business stakeholders were unable to understand the feature integration with the product and raised concerns.
What can the project manager do to demonstrate the feature integration?
Answer options
- A. Include the business stakeholders in the iteration review.
- B. Involve business stakeholders in the iteration retrospective.
- C. Create a task for the iteration review and add it to the backlog.
- D. Review the backlog in detail with the business stakeholders.
Correct answer: A
Explanation
Including the business stakeholders in the iteration review allows them to see the feature in action and understand its integration firsthand. The other options, while valuable in their own right, do not directly provide a demonstration of the feature's integration as effectively as the iteration review does.