Project Management Professional (PMP) — Question 1158
During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain feedback from on project deliverables. What should the project manager do?
Answer options
- A. Share a template with the stakeholder to receive feedback on deliverables.
- B. Use networking skills to approach the stakeholder.
- C. Ask the project sponsor to arrange a meeting with the stakeholder.
- D. Update the stakeholder engagement plan for the stakeholder.
Correct answer: B
Explanation
The correct answer is B because utilizing networking skills can help build rapport and facilitate better communication with the stakeholder. Option A, while helpful, might not address the underlying communication issue. Option C involves relying on the project sponsor, which may not be necessary if direct engagement can be established. Option D implies a change in strategy that may not solve the immediate communication problem.