A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements, the development of the product will take more time than expected. What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because the project manager must ensure that all project-related communications are centralized to maintain clarity and accountability. Options A, C, and D address specific actions but do not prioritize the essential communication aspect that the project manager must establish with both the team and the customer.