Project Management Professional (PMP) — Question 114

During a project's execution phase, two team members are having conflicts with other team members within the team on technical and interpersonal levels.

Which two actions should the project manager take first to address this conflict? (Choose two.)

Answer options

Correct answer: B, E

Explanation

The correct actions are to arrange individual meetings with the conflicting team members (B) and to discuss the conflict directly and collaboratively (E). This allows for a focused resolution without the pressure of a larger audience. The other options either delay resolution (A), involve the entire team unnecessarily (C), or escalate the issue to HR too soon (D).