Project Management Professional (PMP) — Question 1127
A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint. A team member provided ideas to improve the testing process during the sprint retrospective.
What is the next step for the project manager?
Answer options
- A. Document the lessons learned and implement improvements in the next sprint.
- B. Request that all team members think of ideas to improve processes.
- C. Facilitate a daily standup with the team to track the implementation of changes.
- D. Organize a demonstration of the changes in the enterprise system.
Correct answer: A
Explanation
The correct answer is A because documenting lessons learned and applying improvements is essential for continuous improvement in Agile methodologies. Option B is less effective as it does not focus on immediate actions. Option C, while helpful for tracking progress, does not directly address the implementation of improvements. Option D is unnecessary at this stage since the focus should be on refining processes first.