Project Management Professional (PMP) — Question 1122

Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the company's competitive advantage. What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because it allows for a structured approach to include valuable features while adhering to the project timeline. Options B and C disregard the necessary change control process, which could lead to chaos in project management. Option D may lead to unnecessary features being added without proper evaluation of their impact on the project scope and objectives.