Project Management Professional (PMP) — Question 1113
A key business stakeholder sent emails to the developers with complaints based on the last few sprints. The developers forwarded the emails to the project manager but have not yet responded to the stakeholder.
What should the project manager recommend to the developers?
Answer options
- A. Analyze and perform a root cause analysis (RCA).
- B. Add the situation to the issue log.
- C. Forward the emails to the product owner.
- D. Set up a team meeting to discuss a response.
Correct answer: D
Explanation
The correct answer is D because setting up a team meeting allows developers to collaboratively address the stakeholder's concerns and formulate an appropriate response. Options A and B do not directly address the need for communication with the stakeholder, and option C does not ensure that the developers are directly involved in resolving the complaints.