Project Management Professional (PMP) — Question 1107

A project manager finds an unexpected issue halfway through a customer's project. After analysis, the project team determines that the issue will affect the timeline unless more resources are allocated to the project.

What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because it involves transparent communication with the customer, allowing them to make informed decisions about their priorities. Option A is inappropriate as it does not involve the customer's input regarding costs. Option B lacks direct engagement with the customer, and Option C assumes the customer's unwillingness to pay additional costs without consulting them first.