Project Management Professional (PMP) — Question 110
An internal virtual team is meeting daily to review iteration progress, as well as to conduct other technical and follow-up calls with key stakeholders. The team seems to be disengaged.
How should the project manager approach this situation?
Answer options
- A. Reduce the number of internal and external meetings.
- B. Schedule one-to-one meetings and team-building meetings.
- C. Review team assignments and reduce the workload.
- D. Give the team members a few days off to reduce stress_
Correct answer: B
Explanation
Option B is correct because organizing one-to-one and team-building meetings can help improve engagement and foster stronger relationships among team members. The other options may not address the root cause of disengagement; reducing meetings (A) might lead to less communication, while simply reducing workload (C) or giving time off (D) does not directly solve the issue of team engagement.