Project Management Professional (PMP) — Question 110

An internal virtual team is meeting daily to review iteration progress, as well as to conduct other technical and follow-up calls with key stakeholders. The team seems to be disengaged.

How should the project manager approach this situation?

Answer options

Correct answer: B

Explanation

Option B is correct because organizing one-to-one and team-building meetings can help improve engagement and foster stronger relationships among team members. The other options may not address the root cause of disengagement; reducing meetings (A) might lead to less communication, while simply reducing workload (C) or giving time off (D) does not directly solve the issue of team engagement.